§ 158.239. Detail Plan Approval.
After site plan approval either by the site plan review committee or by City Council, detail plans shall be submitted for approval by the site plan review committee. At the applicant's option, the final detail plans may be submitted for review concurrent with the site plan.
(A)
The following detail plan approvals are required prior to the commencement of any development:
(1)
Drainage construction plans, specifications, and calculations.
(2)
Paving and road construction plans and specifications.
(3)
Utility construction plans and water and sewer.
(4)
Clearing plans.
(5)
Grading and excavation plans.
(6)
Plans for all signs.
(7)
Final landscaping plan.
(B)
Detail plans may be approved, approved with conditions or denied by the site plan review committee, pursuant to subsection 158.237(A).
(C)
Appeal of a decision of the site plan review committee shall be to the City Council in accordance with the provisions for appeal set forth within this chapter.
(Ord. No. 98-84, § 1, 3-22-99)